The Third Runway was approved by the Australian Government in September 2024. The approved Major Development Plan (MDP) sets out what will be built and how the impacts will be managed.
Since the approval, further site investigations have been undertaken and detailed design has progressed. This work has provided a clearer understanding of how the runway will be constructed on site.
In some areas, the land required now differs from what was originally planned, with more space needed in some places and less in others. Melbourne Airport is proposing these changes through a Minor Variation to the approved Major Development Plan.
Why it matters:
The proposed changes would reduce the overall construction area. The total area used to build the runway would shrink by about 30 hectares (around 3.6%), from 836.4 to 806 hectares.
Impacts on native habitat would be reduced. Compared with the current plan, the changes would affect about four fewer hectares of native grassland and about five fewer hectares of Growling Grass Frog habitat. They would also reduce impacts on Golden Sun Moth habitat and Grey Box Woodland.
The runway itself is not changing. The runway, its layout, how it will operate, flight paths and the aircraft noise assessment all stay the same.
What we're proposing:
Adjusting the land required for utilities, drainage, local roads and construction access, and temporary and permanent construction areas.
Removing land no longer required. These areas would be excluded from the construction area and protected as "no-go" zones.
Not building the 720-metre approach lighting system for the existing north-south runway. It's no longer part of the project.
Clarifying two pieces of supporting infrastructure. These are utilities for the instrument landing system on the existing north-south runway and an updated layout for the high-voltage power network.
Accessing the preliminary version of the draft Minor Variation
Copies of the preliminary version of the draft Minor Variation are available for inspection and purchase by members of the public during normal office hours throughout the 15-business-day public consultation period, from 24 November 2026 to 14 December 2026.
Copies can be inspected and purchased at the offices of Australia Pacific Airports (Melbourne) Pty Ltd, Level 2, Terminal 4, Melbourne Airport, telephone (03) 9297 1600, between 9.00am and 5.00pm Monday to Friday, excluding public holidays.
A digital copy of the preliminary version of the draft Minor Variation is also available free of charge on this website throughout the 15-business-day public consultation period.
Members of the public are invited to give written comment on the preliminary version of the draft Minor Variation to Australia Pacific Airports (Melbourne) Pty Ltd within 15 business days of the commencement of public exhibition.
Submissions can be made via the 'Make a Submission' tab above, by email to thirdrunwaymdpminorvariation@melair.com.au, or by mail addressed to the Head of Planning, Melbourne Airport, Locked Bag 16, TULLAMARINE VIC 3043.
The closing date and time for receipt of submissions is 11.59pm on 14 December 2026.
Frequently asked questions
No. The runway, taxiways, how the airport operates and how many flights it can handle all stay the same as approved in 2024. The changes are about how the runway is built on the ground, not what is being built.
No. The proposed changes don't affect flight paths or the assumptions used to assess aircraft noise. The aircraft noise assessment in the approved plan still applies.
We expect construction traffic and noise to stay within what was assessed and approved. The types of work, equipment and working hours are the same as approved. There's no significant change to the site entry points, truck routes or peak construction traffic. The management plans already in place will keep applying.
Overall, the changes would reduce impacts on several protected plants, animals and habitats compared with the current approved plan. Land we no longer need will be protected from disturbance. We've done more assessment of soils, groundwater, ecology and historic heritage. We're also working with the Wurundjeri Woi-wurrung Cultural Heritage Aboriginal Corporation to update the Cultural Heritage Management Plan.
The Federal Minister for Infrastructure, Transport, Regional Development and Local Government. Before then, the proposal will be on public exhibition, and anyone can make a submission. We'll consider every submission before we send the final proposal to the Minister.
Make an online submission on the proposed minor variation to the Melbourne Airport Third Runway Major Development Plan
Alternative ways to make a submission
Submit via email
You can email your submission directly to thirdrunwaymdpminorvariation@melair.com.au.
Submit via mail
If you would prefer to make your submission by post, please address your submission to:
Head of Planning
Locked Bag 16
TULLAMARINE VIC 3043
Frequently asked questions
There are three ways that you can make a submission:
1. Use the online form above to make a submission.
2. Email your submission to thirdrunwaymdpminorvariation@melair.com.au.
3. Send your submission via post, addressing it to:
Head of Planning
Melbourne Airport
Locked Bag 16
TULLAMARINE VIC 3043
All submissions received during the public consultation period are reviewed and considered as part of the Major Development Plan process. Feedback is provided to the project team to help inform the final Master Plan and improve our understanding of community and stakeholder views. A summary of the feedback received and how it has been considered will be included in the consultation outcomes reported as part of the Major Development Plan process.
You will receive an automatic acknowledgement when you submit feedback through the online form or by email. However, we will not be providing individual responses to submissions. All submissions received during the public exhibition period will be reviewed and considered as part of the Major Development Plan process, and a summary of the feedback received and how it has been considered will be reported as part of the consultation outcomes.
You can make a submission from Tuesday 24 November 2026 until 11:59pm on Monday 14 December 2026. Submissions will no longer be accepted after that time.